Cooling Tower Inspections
Diagnose, Document, and Plan with Precision

Our inspections deliver actionable data, risk prioritization, and system-level insights.

Ensure Peak Performance with OBR Cooling Tower Inspections

Cooling towers are vital to industrial, commercial, and HVAC systems. Without regular inspections, minor issues can escalate into costly failures, energy inefficiencies, and compliance risks. OBR Cooling Towers offers comprehensive inspections designed to extend equipment lifespan, optimize performance, and prevent downtime.

What’s Included in Our Inspection?

Our team of experts performs an in-depth evaluation of every critical component, providing a detailed assessment with actionable recommendations.

FRP Structure inside a cooling tower

Structural Integrity Check

Evaluation of water basins, wood, fiberglass, steel, and concrete for wear, corrosion, or leaks.

Detection of material fatigue and structural weaknesses.

Cooling Tower Fan Stack with visible fan blades

Mechanical Component analysis

Driveshafts, gearboxes, fans, and motors assessed for alignment, lubrication, and performance.

Belt and bearing condition evaluations to prevent unexpected breakdowns.

French Style Sprayer Nozzle install inside cooling tower

Water Distribution system Assessment

Inspection of nozzles, piping, and fill media to maximize heat transfer efficiency.

Identification of scale buildup, clogging, or water flow inefficiencies.

OSHA Compliance Swing Gate for Ladder Entrance.

OSHA & Safety Compliance Check

Ladder access, guardrails, and other safety components reviewed for compliance.

Identification of potential risks for maintenance teams.

Cooling Tower Technician testing thermal efficiency

Thermal Efficiency Testing

Performance measurement to detect energy inefficiencies.

Assessment of cooling capacity and heat dissipation effectiveness.

OBR Cooling Tower Technician Documenting Inspection Results

Customized Service Recommendations

Detailed report with findings, prioritized repair recommendations, and long-term maintenance strategies.

Immediate and future repair cost estimates.

How Our Inspection Process Works

01.

Initial Consultation

Discuss your cooling tower’s condition and schedule an inspection.

02.

On-Site Inspection

Our specialists conduct a full structural, mechanical, and thermal analysis.

03.

Comprehensive Reporting

Receive a detailed report with findings and recommendations.

04.

Implementation Plan

Work with OBR on the next steps for maintenance or repairs.

What Happens If You Skip Inspections?

Higher Energy Bills

Inefficient systems increase operational costs.

Unexpected Failures

Small issues become catastrophic problems.

Regulatory Non-Compliance

Safety violations can result in hefty fines.

Displaced Nozzle Splash Plate + Grommet inside Cooling Tower

Figure 1: Displaced nozzle splash plate and grommet.

Flex Element Signification Wear inside cooling tower

Figure 2: Cell 11F2 flex element significant wear.

Oil line leak on a pipe in cooling tower

Figure 3: Cell 11F1 oil line leak.

Cooling Tower Pipe Misalignment

Figure 4: Pipe misalignment in Cell 11F3.

Fill Damage Due to Nozzle Displacement

Figure 5: Thirteen fill packs exhibit damage as a result of prolonged water loading caused by damaged or displaced nozzles.

Close-up of a wooden post with visible damage and decay.

Figure 6: Significant internal rot identified in column.

Internal Cooling Tower Wood Structure with Rot and Decay

Figure 7: Significant internal rot identified in brace.

Cooling Tower Wood Structure Bean with Rot and Decay

Figure 8: Further significant internal rot in fan deck longitudinal joist support.

Cooling Tower Wood Structural Post with Rot and decay

Figure 9: Further significant internal rot in fan deck longitudinal and column.

Internal Wooden Structural Posts broken and causing failed tower support

Figure 10: Cell 2 failed transverse brace as a result of excessive rot.

Cooling Tower Internal Wooden Joist Failure with Rot and Decay

Figure 11: Fill support overview (Cell 7F1). Numerous joist supports failed at the column hardware connection.

Collapsed Film Fill Support inside Cooling Tower

Figure 12: Collapsed fill supports on the south side of Cell 7F1.

Collapsed Film Fill Support inside a cooling tower with wood structure

Figure 13: Failed fill joist supports.

Collapsed Fill Media inside a cooling tower

Figure 14: Each top fill pack is fabricated to fit above longitudinal ties. Each fill “lip” is heavily deflected as fill media begins to collapse.

Measurement of separation of fill packs collapsing in cooling tower

Figure 15: Large gap between top and middle 2’ high fill packs.

Corroded gearbox Output Shaft for Cooling tower fan

Figure 16: Heavily corroded gearbox output shaft.

Significant Curb Cracking inside Cooling Tower Basin

Figure 17: Concrete curb significant crack on north side of Cell 5F3.

Vertical Turbines missing Strainers inside cooling tower basin

Figure 18: Three of the four vertical turbines are absent strainers.

Reasons to Work with
OBR Cooling Towers

With over 30+ years of industry experience, OBR Cooling Towers is trusted by hospitals, universities, data centers, and industrial facilities nationwide. Our inspections provide actionable insights that help prevent costly repairs and extend the life of your equipment.

Expert Engineering Team

Specialized in mechanical, structural, and thermal analysis.

Comprehensive Reporting

Receive a full diagnostic report with clear, prioritized recommendations.

fast Response Time

Nationwide coverage with quick turnaround times.

Proven Customer Success

Our inspections have helped clients save thousands in repair costs by identifying issues before they escalate.

Download Our Cooling Tower Inspections Brochure

Want a quick overview of what’s included in an OBR Cooling Tower Inspection?

Our brochure breaks it down for you—with details on:

  • What we inspect (structural, mechanical, thermal, and safety)
  • The value of early detection and proactive planning
  • Real-world benefits like reduced downtime and budget optimization
  • Why timing inspections before planned outages helps avoid costly surprises

 

Whether you're planning next year’s shutdown or reviewing your facility's maintenance strategy, this guide is a great place to start.

 

Schedule Your Professional Cooling Tower Inspection Today!

Contact us today to discuss your inspection needs and receive a detailed assessment.